Dare County’s $8.6 million Buxton terminal groin repair is moving into construction, restoring a critical component of the community’s long-term shoreline management strategy. Coordinated with the ongoing 2026 beach nourishment project, the repair will strengthen the groin’s ability to retain sand, manage erosion, and support protection of Buxton’s oceanfront and N.C. Highway 12.
Rebuilding a Critical Shoreline Structure
SJ Hamill Construction Company is advancing preparations for the terminal groin repair, with equipment staged and large armor stone arriving at the project site. Crews have begun removing existing sheet pile and preparing to construct the temporary trestle that will support armor stone placement and the installation of new sheet piles as work progresses seaward.
Originally constructed to help stabilize the shoreline and reduce erosion, the terminal groin has deteriorated over time from storms and shifting sands. Engineering assessments determined that at least 50 percent of the existing structure remains intact, allowing the groin to be repaired rather than completely replaced.
Coordinating for Long-Term Protection
The terminal groin work is being coordinated with Buxton’s 2026 beach nourishment project, bringing two major shoreline investments together to improve long-term performance. While nourishment restores critically needed sand to the beach and dune system, the rehabilitated structure will help retain that sand and manage sediment movement along this highly dynamic stretch of shoreline.
Construction is expected to be substantially complete by the end of the year, weather and material delivery schedules permitting. Together, these efforts represent a comprehensive approach to reducing erosion, strengthening storm protection, and supporting the long-term resilience of Buxton’s oceanfront.